OUR PROCESS

DESIGN PHASE 

Week 1
  • Preliminary lot meeting and getting to know each other

  • Review examples of previous homes

  • Briefly talk about your envisioned home

Week 2-4
  • Design questionnaire

  • Begin designing home

Week 5-8
  • Homeowner approval of the design

  • Proposal and contract preparations

  • Lender approval

  • Contract signing

BUILD PHASE

Week 1-3
  • Submit for Neighborhood Architectural Review

  • County Permit Applications

  • County and Neighborhood Approval

Week 4-6
  • Lot Clearing

  • Sit Prep

  • Foundation Pouring

Week 7-12
  • Framing

  • Roof Installation

  • Dry-in

Week 13-22
  • Mechanical Installation 

  • Insulation and Drywall Hanging

  • Trim Installation 

Week 23-33
  • Painting

  • Carpeting and Flooring Installation

  • Cabinet Installation 

  • Appliance Installation

  • Closet Shelving Installation

  • Landscaping

  • Final Punchlist Review